Order/Time schedule for cement plastering is following.

Time schedule/Order for cement plastering is following. 
  • Plan the plastering when the surface receiving plaster coat is sufficiently matured. 
  • Ensure that subsequent building operations do not cause any damage in plaster work. 
  • Start external plastering from the top most floors and proceed downwards.
  • Start internal plastering after the structural work is complete. 
  • Do plastering on ceiling wherever required before the walls are plastered.